Caltrans Says Bay Bridge Rods Need to Be Adjusted

View Comments (
)
|
Email
|
Print

    NEWSLETTERS

    Arnab Bose
    The Bay Lights could keep shining on the Bay Bridge until 2026.

    Some of the anchor rods that hold in place strands of the main cable of the Bay Bridge's new eastern span are skewed off-center and will have to be adjusted, a Caltrans spokesman said Saturday.

    However, spokesman Victor Gauthier said, "It's not an urgent issue" and driver safety, seismic safety and the expected 150-year lifespan of the bridge won't be impacted by the problem.

    The concern is that the rods are now close to the sharp-edged plates that are inside the new span and if the rods are jerked in a large earthquake the cable could be damaged and the bridge's stability could be threatened.

    Gauthier said many of the rods, which are essential to the span's structural stability, are less than the required 10 millimeters from the inner surface of the holes through which they pass.

    Engineers Set to Split Old Eastern Span of Bay Bridge in Half

    [BAY] Engineers Set to Split Old Eastern Span of Bay Bridge in Half
    The old eastern span of the Bay Bridge will soon be taken down in phases by engineers. Joe Rosato Jr. reports. (Published Monday, Mar 24, 2014)

    "There's an adjustment that needs to take place so there's adequate clearance," Gauthier said. One possibility is make the holes bigger and the other is to realign the bolts as they go through the holes, he said.

    More Questions Arise About Safety of New Bay Bridge

    [BAY] More Questions Arise About Safety of New Bay Bridge
    Some cable sections and rods on the new San Francisco-Oakland Bay Bridge are rusting, and engineering experts say it could lead to structural damage if the corrosion worsens. Jodi Hernandez reports. (Published Monday, Apr 14, 2014)

    But he said the work can be finished "in several months" while the bride is still in service.

    Gauthier said it's too early to estimate what the repair will cost but he said, "It's definitely not a difficult job."

    New Defect on Eastern Span of Bay Bridge

    [BAY] New Defect on Eastern Span of Bay Bridge
    Authorities discover a new defect on the eastern span of the Bay Bridge. Christie Smith reports. (Published Friday, May 16, 2014)

    Metropolitan Transportation Commission spokesman Randy Rentschler also said it's too soon to estimate the cost but he said it's likely the amount will be in the millions of dollars, not hundreds of thousands of dollars.

    The money for the work will come from the bridge's contingency fund, he said.

    Rentschler said, "It's not an immediate problem" and probably won't be the last issue for the new eastern span, which was a $6.4 billion project and just opened last Labor Day.