Retaining Wall Collapse Blamed for 405 Freeway Project Delay

The collapse led to a 15-month delay for the project through the Sepulveda Pass

By Jacob Rascon and Jonathan Lloyd
|  Monday, Oct 21, 2013  |  Updated 8:28 PM PDT
View Comments (
)
|
Email
|
Print
The 405 freeway widening project is over budget, behind schedule and facing new construction problems. Problems with the retaining walls have delayed the project completion until next fall. Kathy Vara reports from the Sepulveda Pass for the NBC4 News at 6 p.m. on Oct. 21, 2013.

Kathy Vara

The 405 freeway widening project is over budget, behind schedule and facing new construction problems. Problems with the retaining walls have delayed the project completion until next fall. Kathy Vara reports from the Sepulveda Pass for the NBC4 News at 6 p.m. on Oct. 21, 2013.

advertisement
Photos and Videos

Review Blames Retaining Wall Collapse

The project is 15 months behind schedule, but Metro officals say it could have been worse. Jacob Rascon reports for the NBC4 News at Noon on Monday Oct. 21, 2013.
More Photos and Videos

Collapsed retaining walls contributed to a 15-month delay for the San Diego (405) Freeway widening project through the Sepulveda Pass, according to federal investigators.

The vertical retaining walls collapsed in December 2011 along the stretch of freeway that connects the San Fernando Valley with the Westside.  The walls, designed to hold back soil, were replaced, but the problem led to a 15-month delay in the completion of the widening project.

The results of the federal review of the project were first reported by the Los Angeles Daily News. The newspaper reported that metal straps connecting wall panels broke.

The collapse led to several lawsuits involving contractors and subcontractors, according to Metro officials. Some of the lawsuits have already been resolved, according to Metro officials.

The project has included phased closures, including two full closures of the 405 Freeway known as "Carmageddon I and II." One Wilshire Boulevard ramp, a Sunset Bridge ramp and Mulholland Bridge are some of the major upcoming phases of the project.

The project's target completion date is sometime in late 2014.

More Top Stories:

Follow NBCLA for the latest LA news, events and entertainment: iPhone/iPad App | Facebook | Twitter | Google+ | Instagram | RSS | Text Alerts | Email Alerts

Get the latest headlines sent to your inbox!
View Comments (
)
|
Email
|
Print
Leave Comments
What's New
Running Dry
Coverage of the California drought. Read more
Follow Us
Sign up to receive news and updates that matter to you.
Send Us Your Story Tips
Check Out